Skip to content

There is no apples-to-apples cost for building an American home.

Construction cost per square foot is quoted everywhere, and each source counts different things. One European study shows how to compare them fairly. The US has no standard.

  • November 27, 2026
  • 32 sources
  • 10 minute read

The cheapest building per square foot costs the most per home

In 2023, BAE Urban Economics priced five common Portland housing types for the city on the same assumptions: townhomes, a surface-parked apartment building, a four-story building with tuck-under parking, a six-story podium building and a 30-story tower.1

Five Portland buildings, priced by one firm on the same assumptions in 2023. 1

Construction cost only, divided by building area.

  1. Townhomes4 homes of about 1,500 sq ft, no parking cost$185/sq ft1
  2. Surface-parked apartments40 homes on a half acre, wood frame, 20 surface stalls$260/sq ft2
  3. Four stories, tuck-under parking64 homes, at-grade parking wrapped by retail$260/sq ft3
  4. Six-story podium143 homes over an underground garage$348/sq ft4
  5. 30-story tower532 homes, concrete or steel, underground garage$414/sq ft5

Rank 1 is the cheapest; the townhome is highlighted. Building area is each project’s total floor area divided by its homes, so the apartment figures include corridors, stairs and, for the four-story, podium and tower buildings, ground floor space such as retail, and the per home costs carry that space too.

The three square-foot measures rank the buildings the same way, with the townhome cheapest at $185 to build. Per home, the townhome falls from first to last at $506,050, $12,616 more than a home in the 30-story tower, and the surface-parked apartments become the cheapest at $287,464. The reason is size and land: each townhome is about 1,500 square feet on $100,000 of land, against about 700 square feet of building per apartment by our arithmetic. Cost per square foot rewards large homes and cost per home rewards small ones, which is why a fair comparison needs both.

What each home costs, piece by piece. Same study.
  • Land
  • Construction
  • Parking
  • Design and other soft costs
  • City fees
  • Financing and developer fee
  1. Townhomes$506,050/home
  2. Surface-parked apartments$287,464/home
  3. Four stories, tuck-under parking$302,668/home
  4. Six-story podium$422,662/home
  5. 30-story tower$493,434/home

Every cost per square foot also makes four choices, and a figure that does not state them cannot be compared with another:

  • Which area. Gross or net, measured to the inside face of a wall or its centerline. The US multifamily area standard offers more than one method.2
  • Which costs. Construction only, or parking, land, fees, design and financing too.
  • Which building. A townhome, a podium and a tower are different products, with or without a garage.
  • Where and when. Labor markets, taxes and the price date all move the number.

Parking, podiums and wraps are where comparisons break

A stall on a surface lot costs a few thousand dollars to build. In a garage it costs tens of thousands.13 Set the type and the number of stalls per home to see what parking adds to the Portland podium building.

What one parking stall costs to build. Land not included, so a surface lot looks cheaper than it is.
  1. Surface lot, PortlandBAE: $100,000 for 20 spaces1$5,000/stall
  2. Wrap garage, TexasAn architecture firm’s planning range4$20,000 to $35,000
  3. Aboveground garage, 17-city averageUCLA, 2025 data3$52,000/stall
  4. Underground garage, Portland podiumBAE: $4.32 million for 72 spaces1$60,000/stall
  5. Underground garage, 17-city averageUCLA, 2025 data3$73,000/stall

Adds $30,000 a home, $43 a square foot of the podium building’s area, or 12% on top of its construction cost.

The stall costs come from different places and methods: Portland, Texas and a 17-city average. They show the range, and are not a like-for-like ranking.

Podiums and wraps make the split harder. In a podium building the garage sits under the homes on a concrete slab that also carries them, so part of the structure serves both. In a wrap, the homes surround a freestanding concrete garage. No independent cost per stall for a wrap garage was found; the Texas range above is one architecture firm’s planning figure.4 RAND counts wraps and podiums as separate building types, and found that engineers expected a California wrap’s garage to cost 15% less without seismic rules.5

Published figures often leave unstated whether parking is inside them, and the major cost guides disagree. Turner & Townsend’s global survey leaves parking out.6 Rider Levett Bucknall leaves it out in Sydney7 and includes an allowance in Singapore and Tokyo.8 WGI’s parking survey leaves out underground garages.9

Driverless cars may shrink the need for parking, but only modeling supports that so far. A Waymo-funded University of Oregon study found large gains in one car-oriented San Francisco neighborhood only if shared, pooled vehicles came to dominate travel across the metro area.10 Garages built for later conversion cost more: one architect’s case study put the premium at 54%.11 No completed conversion of a garage built for it was found.

A 10- to 12-story building crosses two code thresholds

Wood frame apartments usually top out at 80 to 85 feet. Above that, a building needs mass timber, steel or concrete.12 The building code also treats a building as high-rise once an occupied floor sits more than 75 feet above fire department access, which brings added fire and life safety requirements such as smoke removal and a fire command center.13 At typical floor heights that line falls around the seventh or eighth story (our estimate), so a 10- to 12-story building sits past both lines. Terner warns that costs from its five-over-one prototype should not be carried to other building types for this reason.14

$420a square foot to build a 150-home mass timber building over 100 feet tall in Seattle, by BAE’s 2025 estimate.12
$450a square foot for a 30-story concrete or steel tower in the same study, a much taller building.12

A firm that designs mass timber put a 12-story Denver building at $19 a square foot, or 3%, more than the same building in concrete.15 No independent figure for a 10- to 12-story concrete apartment building was found. Pricing one 12-story reference building in both materials, in every metro on one date, would show that gap where it applies.

Homebuilders publish one cost per square foot every quarter; apartment developers do not

$80a square foot to build a Lennar detached home, down 14% since late 2023.16
$78a square foot for a PulteGroup detached home.17

These are company-reported averages for detached houses across many plans and markets, reported to investors. Pulte reports lot costs separately and Lennar does not publish a definition, so they do not compare with the apartment figures above. They can be tracked because each company defines the number the same way every quarter. Lennar credits part of the decline to standardizing features to capture purchasing efficiency16 and to a shift toward a core product that is “smaller product, easier to build, lower cost.”18

Apartment developers report a total capital cost and an expected yield for each community. AvalonBay started 3,888 homes in 2025 at a total capital cost of $1.64 billion, which works out to about $421,000 a home by our arithmetic, including land and some commercial space. No breakdown is published that another developer could compare.19

Researchers build their own data because no standardized dataset exists

For its 2020 study of construction costs, the Terner Center coded the line items of more than 240 California projects to one standard, partly by hand. It found that understanding hard costs “is difficult due to the lack of publicly-available, detailed data on specific projects.”20 A 2018 national study of tax credit projects collected building type and then left it out, because too many projects did not report it.21

RAND compared market-rate apartments across states in 2025: $415 a rentable square foot in California against $157 in Texas, all-in, in 2019 dollars.5 It adjusted for building type, unit size and region because the ideal study, the same building priced in different places at the same time, was out of reach. None of these studies proposes a national standard. The closest call came from GAO.

The clearest federal call for comparable housing cost data.2223
  1. 2018GAO finds wide cost variation in tax credit housing and data too inconsistent to fully explain it. It asks Congress to name an agency to collect cost data, and the IRS to push for standard definitions.
  2. 2018The IRS disagrees, saying it lacks the authority to collect the data.
  3. 2023GAO repeats that no federal agency has the authority to collect and report the data.
  4. 2026As of February, Congress has not acted.

One building priced in ten cities shows how a fair comparison works

In 2024 the Society of Chartered Surveyors Ireland and Trinity College Dublin ran the study RAND could not. They took one seven-story, 39-home apartment building, first built in Switzerland, and had surveyors in ten European cities price the same 317 items.24 Everyone used the same cost categories, the same floor area of 4,015 square meters and the same price date, the first quarter of 2020, chosen to come before the price swings of the pandemic and the war in Ukraine. Land, design fees and financing were left out.

The same 39-home building, priced in ten cities. Euros per square meter, first quarter of 2020, each country’s VAT included.24
  1. Tallinn€1,367
  2. Belfast€1,367 to 1,823
  3. Brussels€1,367 to 1,823
  4. Amsterdam€1,823
  5. Birmingham€2,079
  6. Glasgow€2,124
  7. Stockholm€2,100 to 2,250
  8. Manchester€2,100 to 2,250
  9. Dublin€2,363
  10. Zurich€2,866

The report’s ten-city average, €2,057. The report gives four cities only as bands, such as between Tallinn and Amsterdam.

Zurich cost more than twice as much as Tallinn. The report found that materials prices varied far less than labor-intensive work, so labor cost and productivity play a large part in the gap. Tax matters too: VAT is 0% in the UK, 13.5% in Ireland and 21% in Belgium, and the report finds that at the UK’s rate Dublin would fall from second to fifth.

The US has an area rule and an element list, and no standardized cost data

A cost standard needs four parts: one way to measure floor area, one list of cost categories, a database of completed projects and a way to compare one building across places. The international cost categories are backed by a coalition of 49 organizations.25 The UK and Germany each have a paid national database of completed projects built on their own categories. Eurostat has adopted the Irish study’s building as one of its models for collecting cost data, but no national program that prices it across cities was found.

The four parts of a cost standard, and who has them.
What a standard needsUnited States226272829United Kingdom3031Germany32Irish study (2024)24
A rule for measuring floor areaHas itBOMA multifamily standard (2023), written for leasingHas itRICS gross internal areaHas itDIN 277Has itInternational Property Measurement Standards
A fixed list of cost categoriesHas itUniFormat II (ASTM E1557) classifies building elementsHas itNRM 1Has itDIN 276Has itInternational Cost Management Standard, 3rd edition
A database of completed projectsPartlyDesignCost Data sells case studies coded by trade; NAHB surveys single-family costs. Neither covers apartments nationally in one set of cost categoriesHas itBCIS, paidHas itBKI, paidNot part of the study
A way to compare one building across placesPartlyRSMeans model buildings, national unit costs adjusted by a city index (commercial)PartlyBCIS location factors, a regional index built from project dataPartlyBKI regional factors, a regional indexHas itOne building priced by surveyors in ten cities

A fair comparison needs fixed reference buildings and separate numbers

The Irish method carries to the US. Fix a design and a bill of quantities for each building type the country needs most, and price them in each metro and in peer countries on the same date. Pricing the mid-rise with and without its garage settles the podium and wrap question without an allocation rule.

Fixed reference buildings, each priced the same way in every metro and reported as three numbers.
  • TownhomeThree stories, wood frame, about 1,500 sq ft of living area. An attached garage is priced as parking
  • Mid-riseFive stories of wood frame, priced three ways: on grade with surface parking, over a podium garage, and wrapped around a garage
  • TowerTwelve stories, priced twice: mass timber and concrete
  1. BuildingCost per square meter and per square foot of gross internal floor area above ground, excluding parking, measured to IPMS and grouped by the ICMS cost categories as the Irish study did, plus cost per home
  2. ParkingThe difference between the mid-rise priced on grade and priced over or wrapped around a garage, reported per stall with the site area each version needs. No rule is needed to split a podium
  3. SiteSite work per home

The tower is priced without a garage, so this method gives no parking figure for towers in a first round. Each metro prices a stated labor basis: open shop, union or prevailing wage. Local code changes, such as seismic and energy rules, are a separate line, as is sales and use tax, and each round states its price date. Land, fees and financing stay out of the comparison and are reported on their own. With parking on its own line, the building figure stays comparable as parking requirements fall, whether or not driverless cars arrive.

The Irish study was run by a professional society and a university. A US version could sit with a university housing center, a cost-surveying body or HUD’s research office. The cheapest first step moves toward GAO’s 2018 recommendation: state housing finance agencies already collect certified costs for tax credit projects, and could ask for them in one set of cost categories. Those projects carry affordable housing rules and often prevailing wage, so they would not stand in for market-rate costs.

Sources

  1. BAE Urban Economics for the Portland Housing Bureau, Residential Development Cost Study (draft memorandum), January 30, 2024, Table 2. Costs are 2023. https://www.portland.gov/phb/documents/residential-development-cost-study-2024/download
  2. BOMA International, BOMA 2023 for Multi-Family and Hospitality (ANSI/BOMA Z65.4). https://boma.org/BOMA/BOMA-Standards/BOMA_Floor_Measurement_Standards/Multi-Family_Hospitality.aspx
  3. UCLA Institute of Transportation Studies, New report: No such thing as free parking, February 19, 2026, covering 17 US cities (2025 Rider Levett Bucknall cost data, land excluded). https://www.its.ucla.edu/2026/02/19/no-such-thing-as-free-parking
  4. Temelar (architecture firm), Garden, wrap and podium apartment building types in Texas, October 17, 2026. A practitioner planning range; method not stated. https://temelar.com/blog/apartment-building-type-garden-wrap-podium-texas
  5. Jason M. Ward and Luke Schlake, The High Cost of Producing Multifamily Housing in California: Evidence and Policy Recommendations, RAND RR-A3743-1, April 2, 2025, comparing California with Colorado and Texas. Costs per net rentable square foot, 2019 dollars. https://www.rand.org/t/RRA3743-1
  6. Turner & Townsend, Global Construction Market Intelligence, methodology (exclusions include underground or on-site car parking unless stated). https://publications.turnerandtownsend.com/global-construction-market-intelligence-2025/methodology
  7. Rider Levett Bucknall, Riders Digest Sydney 2026 (building rates exclude car parking, which is priced per car). https://www.rlb.com/wp-content/uploads/sites/1/2026/01/2026-RLB-Rider-Digest_Sydney_Digital_2.pdf
  8. Rider Levett Bucknall, Singapore Regional Report, December 2025 (condominium rates include a car park allowance; Tokyo rates on the same basis). https://www.rlb.com/wp-content/uploads/sites/5/2026/02/Singapore_Reg-Report-Dec-2025-Final-Compressed.pdf
  9. WGI, Parking Structure Cost Outlook for 2024 (freestanding above-grade garages; garages entirely or significantly below grade excluded). https://publications.wginc.com/hubfs/WGIs%20Parking%20Structure%20Cost%20Outlook%20for%202024.pdf
  10. Urbanism Next Center (University of Oregon) with ECONorthwest, Potential impacts of autonomous vehicle deployment on parking, 2023, funded by Waymo. https://www.urbanismnext.org/resources/potential-impacts-of-autonomous-vehicle-deployment-on-parking
  11. William F. Kavanagh, Parking Garages: A Contrarian Perspective, AIA Philadelphia, May 19, 2025. https://aiaphiladelphia.org/news/context-spring-2025/1417/1417-Parking-Garages-A-Contrarian-Perspective-
  12. BAE Urban Economics for the City of Seattle, Real Estate Financial Feasibility Technical Report, Downtown Regional Center Plan, March 25, 2025. https://seattle.gov/documents/Departments/OPCD/OngoingInitiatives/UrbanCentersPlanning/Downtown/Appendices/OPCDRegionalCentersPlanningDowntownAppendixRealEstateFinancialFeasibilityReport.pdf
  13. International Code Council, 2021 International Building Code, Chapter 2 (definition of high-rise building) and Section 403 (high-rise buildings). https://codes.iccsafe.org/content/IBC2021P2/chapter-4-special-detailed-requirements-based-on-occupancy-and-use
  14. Terner Center for Housing Innovation, Making It Pencil, December 2023. https://ternercenter.berkeley.edu/wp-content/uploads/2023/12/Making-It-Pencil-December-2023.pdf
  15. SCB (architects), Mass timber for multifamily housing, June 30, 2025. A practitioner estimate from a firm that designs mass timber. https://scb.com/2025/06/30/mass-timber-for-multifamily-housing-sustainable-fast-and-beautiful/
  16. Lennar, third quarter 2026 earnings call transcript, September 17, 2026 (company-reported). https://investors.lennar.com/~/media/Files/L/Lennar-IR-V3/reports-and-presentations/q3-2026-len-earnings-call-transcript.pdf
  17. PulteGroup, fourth quarter 2025 earnings call, January 29, 2026 (company-reported). https://www.fool.com/earnings/call-transcripts/2026/01/29/pultegroup-phm-q4-2025-earnings-call-transcript
  18. Lennar, second quarter 2026 earnings call transcript, June 12, 2026 (company-reported). https://investors.lennar.com/~/media/Files/L/Lennar-IR-V3/reports-and-presentations/q2-26-len-earnings-call-transcript.pdf
  19. AvalonBay Communities, fourth quarter 2025 earnings release (company-reported). Per home is our arithmetic. https://investors.avalonbay.com/_assets/_3cbf65c3520f79ee3b031747dbd5d004/avalonbay/db/2294/21791/earnings_release/Q4+2025+Earnings+Release.pdf
  20. Terner Center for Housing Innovation, The Hard Costs of Construction: Recent Trends in Labor and Materials Costs for Apartment Buildings in California, March 2020. https://ternercenter.berkeley.edu/wp-content/uploads/2020/08/Hard_Construction_Costs_March_2020.pdf
  21. Abt Associates for the National Council of State Housing Agencies, Variation in Development Costs for LIHTC Projects, August 30, 2018. https://ncsha.org/wp-content/uploads/2018/09/Final-LIHTC-Costs-Analysis_2018_08_31.pdf
  22. U.S. Government Accountability Office, Low-Income Housing Tax Credit: Improved Data and Oversight Would Strengthen Cost Assessment and Fraud Risk Management, GAO-18-637, September 2018 (status as of February 2026 on the same page). https://www.gao.gov/products/GAO-18-637
  23. U.S. Government Accountability Office, Low-Income Housing Tax Credit: Opportunities to Improve Oversight, GAO-24-107064, December 2023. https://www.gao.gov/products/gao-24-107064
  24. Society of Chartered Surveyors Ireland and Trinity College Dublin, Building Homes: Apartment Construction Costs in Europe with a Focus on Dublin, July 2024. https://tcd.ie/media/tcd/news-images/SCSI-TCD-Building-Homes-Report.pdf
  25. ICMS Coalition of 49 organizations, International Cost Management Standard, 3rd edition (2021). https://icms-coalition.org/
  26. ASTM E1557, Standard Classification for Building Elements and Related Sitework (UniFormat II), reapproved 2024. https://webstore.ansi.org/standards/astm/astme1557092024
  27. DesignCost Data, About: more than 2,200 completed project case studies, costs organized by CSI MasterFormat (subscription). https://dcd.com/about-us/
  28. NAHB, Cost to construct a home rose significantly over last two years (Cost of Constructing a Home survey, 2024), January 2025. National averages for single-family homes by cost category. https://www.nahb.org/blog/2025/01/cost-to-construct-a-home-rose-significantly-over-last-two-years
  29. RSMeans (Gordian), Square Foot Costs 2026: modeled costs for model buildings, adjusted for more than 930 locations (commercial). https://www.rsmeans.com/media/wysiwyg/product_pdf/2026-SQFT-TOCs.pdf
  30. RICS, NRM 1: Order of cost estimating and cost planning for capital building works, 3rd edition (in force December 1, 2021). https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM1_Oct2022.pdf
  31. BCIS CapX: cost analyses of more than 21,000 completed projects (subscription). https://www.bcis.co.uk/product/bcis-capx/
  32. BKI Baukosten Gebaeude Neubau 2025: costs of completed projects per square meter by German cost group (DIN 276) and floor area (DIN 277). https://www.baunetzwissen.de/controlling-und-management/tipps/buecher/bki-baukosten-gebaeude-neubau-2025-9882825

Figures are as published by each source; per square foot and per home figures for the Portland buildings are our arithmetic from BAE’s table. Corrections: team@nowcitylabs.com.

Work with us.

Commission deeper research and reporting. Or get help building your industrialized construction value chain: partnerships, cost estimates and deal structures.