# ATCO Structures

Makes, sells and leases modular workforce housing, offices and homes from 13 plants in five countries. A unit of ATCO Ltd.

- **Operating status:** Active. ATCO reported in February 2026 that manufacturing had begun on a 1,052-person lodge for the Stibnite Gold Project in Idaho. Its 2025 report says the wholly owned unit added a plant in Queensland and ended the year with 13 manufacturing facilities. [3][1]
- **Momentum:** Expanding
- **Ownership:** Part of ATCO Ltd.
- **Headquarters:** Calgary, Alberta, Canada
- **Role:** Manufacturer, Builder
- **Method:** Volumetric modules
- **Product:** Room modules, Whole homes
- **Builds:** Workforce housing, Commercial, Single-family, Multifamily, Emergency shelter
- **Website:** https://structures.atco.com/ (loaded when checked)

Checked 2026-11-19. Page: https://nowcitylabs.com/fieldguide/construction/p/atco-structures/

## Summary by the Lead Analyst

ATCO Structures is the modular manufacturing and leasing arm of Calgary's ATCO Ltd. Its parent's filings document 13 plants, more than 28,500 rental units and a C$179 million contract for a 1,052-person lodge in Idaho. Two US plants, in Texas and Idaho, are named only in 2012 and 2020 sources and their current status was not confirmed. Energy, waste and workforce figures for the unit are not public in the sources reviewed.

Verify first: Ask which plant would build the modules. The Diboll and Pocatello plants are confirmed only by 2012 and 2020 sources.

## What it is

ATCO Structures is the founding business of ATCO Ltd., which owns all of it through ATCO Structures & Logistics. It manufactures, sells and leases transportable workforce housing, space rental units and residential modular housing. ATCO's 2025 report counts 13 manufacturing facilities in five countries and a fleet of more than 28,500 rental units, of which 1,983 were workforce housing units. [1]
Its largest US contract is a C$179 million award from Perpetua Resources in October 2025 to design, supply and install a 1,052-person dormitory lodge and offices at the Stibnite Gold Project near Yellow Pine, Idaho. The lodge uses 363 modular units and is due to be operating in the first quarter of 2027. [2]
Other 2025 US awards covered workforce housing and space rentals for data center construction in Texas, power generation, mining and chip plants. Bloomberg reported in March 2026 that the unit had quoted 40 to 50 data center housing projects, from a 50-bed camp to a 6,000-person development. [1][6]

## Key facts

- Headquarters: Calgary, Alberta [1]
- Factory: 13 plants in five countries (2025) [1]
- Rental fleet: More than 28,500 units (2025) [1]
- Workforce fleet: 1,983 units, 58 percent average utilization (2025) [1]
- Ownership: ATCO Ltd., 100 percent [1]
- Serves: Canada, United States, Australia [1]

## Production and technology

- Production: No data
- Technology: No data

## Card fields

The same twelve fields every card, table row and comparison shows. A missing value says why: No data, Not published, N/A or Not yet rated.

- Method: Volumetric modules
- Materials: No data
- Products: Room modules, Whole homes
- Building markets: Workforce housing, Commercial, Single-family, Multifamily, Emergency shelter
- Factory: Diboll, TX; Pocatello, ID
- Markets served: Canada, United States, Australia
- Demonstrated scale: 28,500 units in fleet, 2025
- Annual capacity: No data
- Cost: Not published
- Green: Not yet rated
- Value: Not yet rated
- Evidence: Strong · Checked Nov 2026

## Measured

- Fleet: 28,500 units in fleet, 2025 (company-reported rental fleet, more than 28,500 units of all types) [1]

## Factories

- Diboll, Texas, United States: Named as a production site in a 2020 project profile [4]
- Pocatello, Idaho, United States: 200,000 sq ft, Announced 2012; named as a production site in 2020 [5][4]

## Serves

- Canada (CA) [1]
- United States (US) [1]
- Australia (AU) [1]

## Timeline

- 2012-04 (factory): Announced a 200,000 square foot plant in Pocatello, Idaho, described as its third in the United States, with more than 150 jobs planned. [5]
- 2020-09 (milestone): Supplied 1,800 beds in 360 units for emergency responders after Hurricane Laura, between September and December 2020, drawing fleet units from across the United States. [4]
- 2022 (acquisition): Acquired Triple M Housing Ltd. [1]
- 2024 (acquisition): Acquired NRB Limited. [1]
- 2025 (factory): Added a manufacturing facility in Brisbane, Queensland and began modernizing its Grimsby, Ontario plant. [1]
- 2025 (milestone): Awarded a Multiple Award Schedule contract by the US General Services Administration. [1]
- 2025-10-27 (milestone): Awarded a C$179 million contract by Perpetua Resources for a 1,052-person lodge and offices at the Stibnite Gold Project in Idaho, the largest US contract in its history. [2][1]
- 2025-12 (milestone): In the fourth quarter of 2025, won C$29 million of sale and lease contracts for 337 modular units supporting education and data center construction in Texas. [1]
- 2026-02-25 (milestone): ATCO reported that manufacturing had begun for the Stibnite lodge. [3]

## Findings by five AI specialists

A level is the strength of the public evidence for one specialist, on a scale of 0 to 4. It is not a grade of the company, and there is no total.

### Materials and Circularity: Specifics published (level 2)

A 2020 project profile shows fleet reuse in practice: 1,500 leased beds drawn from units held across the US. The 2025 report says under-used workforce units were sold. No waste, material or end-of-life data is published.

- Evidence: The Hurricane Laura profile lists 1,500 beds on leased units and 300 on purchased units, with fleet units gathered from multiple US locations. [4]
- Evidence: The 2025 report says the global workforce housing fleet was reduced by disposing of under-utilized assets. [1]
- Gap: Factory waste, materials, unit service life, and whether any lodge is designed for conversion to permanent housing.

### Energy and Carbon: No public evidence (level 0)

No public evidence found on the energy performance or carbon of its buildings in the sources reviewed.

- Gap: Energy standards met by its workforce and residential modules, and any measured or verified figure.

### Cost and Access: Specifics published (level 2)

One price is public: C$179 million for a 1,052-person lodge and offices in Idaho, signed in October 2025. The parent describes attainable residential housing as a goal, without prices or counts of homes.

- Evidence: The October 2025 release gives the contract value and the 1,052-person, 363-unit scope. [2]
- Evidence: The 2025 report says the unit produces affordable modular products including attainable residential housing. [1]
- Gap: Prices for its residential homes, and counts of affordable homes delivered.

### Workforce: Specifics published (level 2)

Jobs are documented only at announcement: more than 150 planned at Pocatello, Idaho in 2012. The parent reports about 21,000 employees across all its businesses. No current plant headcount or injury rate for the unit was found.

- Evidence: IndustryWeek reported more than 150 full-time positions planned at the Pocatello plant in 2012. [5]
- Evidence: The October 2025 release gives about 21,000 employees for ATCO Ltd. as a whole. [2]
- Gap: Current headcount and injury rates at each plant, and whether the Diboll and Pocatello plants are operating.

### Delivery Record: Third-party evidence (level 3)

The listed parent's 2025 report gives 13 plants, more than 28,500 rental units and C$119 million of adjusted earnings for the unit. Bloomberg reported its US data center bids and the release documents the Idaho contract.

- Evidence: The 2025 report gives 13 manufacturing facilities, a fleet of more than 28,500 units and adjusted earnings of C$119 million for ATCO Structures. [1]
- Evidence: Bloomberg reported 40 to 50 data center housing quotes in March 2026. [6]
- Evidence: Earlier US projects named in the release include a 2,300-person LNG construction facility in Louisiana and a 1,500-person wildfire shelter in Paradise, California. [2]
- Gap: A list of plants by location, and completed lodge projects with dates and bed counts.

## Sources

1. [ATCO Ltd. Management's Discussion and Analysis for the year ended December 31, 2025](https://www.atco.com/content/dam/atco-website/en-ca/web/assets/investors/atco-2025-ye-mda.pdf) (ATCO Ltd.)
2. [ATCO Structures Accelerates U.S. Expansion with $179M Worker Housing Contract for Perpetua Resources](https://www.newswire.ca/news-releases/atco-structures-accelerates-u-s-expansion-with-179m-worker-housing-contract-for-perpetua-resources-881668994.html) (ATCO Ltd. via CNW)
3. [ATCO Reports 2025 Earnings](https://www.newswire.ca/en/releases/archive/February2026/26/c2394.html) (ATCO Ltd. via CNW)
4. [Hurricane Laura Response Project profile](https://structures.atco.com/content/dam/web/for-business/structures-usa/hurricane-laura-response-usa-2020-v2-project-profile.pdf) (ATCO Structures)
5. [New Idaho Plant to Meet Growing Demand for Modular Housing in Energy](https://www.industryweek.com/expansion-management/industry-clusters/article/21935376/new-idaho-plant-to-meet-growing-demand-for-modular-housing-in-energy) (IndustryWeek)
6. [AI 'Man Camps' Offer Golf, Free Steaks to Lure Workers in Texas (Bloomberg, March 6, 2026)](https://www.insurancejournal.com/news/southcentral/2026/03/06/860884.htm) (Insurance Journal, republishing Bloomberg)