# Harmet

Estonian maker of timber-frame housing modules, site huts and bathroom pods, sold mostly to Scandinavia.

- **Operating status:** Active. Its site is live and says it runs three factories, with the Kumna plant able to make about 3,600 modules a year. [2]
- **Momentum:** Unknown
- **Ownership:** Unknown
- **Headquarters:** Kumna, Harju County, Estonia
- **Founded:** 1992
- **Role:** Manufacturer, Builder
- **Method:** Volumetric modules
- **Material:** Light wood frame
- **Product:** Room modules, Bathroom pods, Whole homes
- **Builds:** Multifamily, Workforce housing, Student housing, Hospitality, Senior housing, Commercial
- **Website:** https://www.harmet.ee/ (loaded when checked)

Checked 2026-11-20. Page: https://nowcitylabs.com/fieldguide/construction/p/harmet/

## Summary by the Lead Analyst

An Estonian company founded in 1992 that has made modules since 1997 and sells more than 90 percent of output in Scandinavia. Its Kumna factory has 22,000 square meters of production area and a stated capability of about 3,600 modules a year. Its reference list gives module counts for Swedish apartment projects. A company product sheet names the USA among export markets, but no United States or Canadian project is named in the sources read. Prices and owners are not public.

Verify first: Any named project delivered in North America, and current headcount, which sources put at over 300 and about 800.

## What it is

Harmet makes timber-frame modular apartment buildings, relocatable modules for schools, offices and worker accommodation, construction site huts, bathroom pods and metal structures, and offers design through assembly. It says more than 90 percent of its output is sold in Scandinavian countries. [1][3]
The company says it operates three factories. The newest, at Kumna near Tallinn, has 22,000 square meters of production area and a capability of about 3,600 modules, or about 130,000 square meters, a year. The contractor Nordecon announced the Kumna building in 2016 at 26,845 square meters in total, due in July 2017. Metsä Wood, a supplier, wrote in 2020 that Harmet had about 800 employees across five factories in Estonia and Finland and that its main clients were Cramo and BoKlok. The company site today says it employs over 300 people. [1][2][5][6]
Its reference list includes 29 BoKlok Classic projects across Sweden totaling 74,421 square meters, a 528-module, 212-apartment project at Bunkeflostrand, apartment buildings in Bodø and Mo i Rana in Norway, and summer houses in the Netherlands. A product sheet for a 44-person worker housing block of 26 modules says more than 95 percent of 2022 turnover of over 100 million euros was exported to Sweden, Norway, Finland, Denmark, the UK, the Netherlands and the USA. [3][7]

## Key facts

- Founded: 1992; modules since 1997 [1][6]
- Headquarters: Kumna, Harju County, Estonia [4]
- Factory: Kumna, 22,000 sq m; also Pärnu and Saue [1][2]
- Employees: Over 300, per the company; about 800 in 2020 [1][5]
- Serves: Over 90 percent sold in Scandinavia [1]

## Production and technology

- Production: Large central factory, Estonian factories sell over 90 percent of output to Scandinavia [1]
- Technology: Automated production, Weinmann CNC machine among its production equipment [2]

## Card fields

The same twelve fields every card, table row and comparison shows. A missing value says why: No data, Not published, N/A or Not yet rated.

- Method: Volumetric modules
- Materials: Light wood frame
- Products: Room modules, Bathroom pods, Whole homes
- Building markets: Multifamily, Workforce housing, Student housing, Hospitality, Senior housing, Commercial
- Factory: Kumna, Estonia; Pärnu, Estonia; Saue, Estonia
- Markets served: Sweden, Norway, Finland, Netherlands, Denmark, United Kingdom, United States
- Demonstrated scale: Not published
- Annual capacity: 3,600 modules a year, reported 2026
- Cost: Not published
- Green: Not yet rated
- Value: Not yet rated
- Evidence: Partial · Checked Nov 2026

## Measured

- Capacity per year: 3,600 modules/yr capacity, reported 2026 (company-reported capability of the Kumna factory, approximate) [2]

## Factories

- Kumna, Harju County, Estonia: 236,806 sq ft, 22,000 sq m production area, about 3,600 modules a year [2]
- Pärnu, Pärnu County, Estonia [4]
- Saue, Harju County, Estonia [1]

## Serves

- Sweden (SE) [3]
- Norway (NO) [3]
- Finland (FI) [3]
- Netherlands (NL) [3]
- Denmark (DK) [7]
- United Kingdom (GB) [7]
- United States (US) [7]

## Timeline

- 1992 (founded): Founded in 1992, per the contractor Nordecon. [6]
- 1997 (milestone): Began making prefabricated modules, per the company. [1]
- 2016-08 (factory): Nordecon announced a contract to build a 26,845 square meter production building for Harmet at Kumna, due in July 2017. [6]
- 2020-03 (milestone): Metsä Wood reported about 800 employees, five factories in Estonia and Finland, and over 3,600 modules a year from Kumna. [5]
- 2022 (milestone): Turnover passed 100 million euros with more than 95 percent exported, per a company product sheet. [7]

## Findings by five AI specialists

A level is the strength of the public evidence for one specialist, on a scale of 0 to 4. It is not a grade of the company, and there is no total.

### Materials and Circularity: Specifics published (level 2)

The company states ISO 14001 certification and describes a worker housing design whose modules can be dismantled and reused at another site. No waste figure or record of a relocated building is published.

- Evidence: The production page states operation under ISO 9001 and ISO 14001. [2]
- Evidence: A product sheet says the 26-module worker housing block can be dismantled and reused in another location. [7]
- Gap: Factory waste by weight and an example of modules that were moved and reused.

### Energy and Carbon: Claims only (level 1)

The company describes timber-frame modules as a low carbon solution. No energy rating, embodied carbon figure or verifier was found.

- Evidence: A company product sheet calls its timber-frame worker housing a low carbon solution. [7]
- Gap: Embodied carbon per square meter and measured energy use of a delivered building.

### Cost and Access: No public evidence (level 0)

No price per module or per apartment was found, and no source says who occupies the housing it supplied.

- Gap: Prices, and whether any delivered apartments are affordable or social housing.

### Workforce: Specifics published (level 2)

Headcount figures differ by source and date: the company site says over 300 people, a supplier article in 2020 said about 800, and a contractor release in 2016 said over 400. No source explains the difference.

- Evidence: The company page says Harmet employs over 300 people. [1]
- Evidence: Metsä Wood reported about 800 employees in March 2020. [5]
- Gap: A dated headcount, any layoffs between 2020 and 2026, and safety data.

### Delivery Record: Third-party evidence (level 3)

A contractor release and a supplier article confirm the Kumna factory and its output of about 3,600 modules a year. The reference list gives module counts for named Swedish projects. No North American project is named.

- Evidence: Nordecon announced the Kumna factory contract in 2016. [6]
- Evidence: Metsä Wood reported over 3,600 modules a year from Kumna. [5]
- Evidence: The reference list includes a 528-module, 212-apartment project in Sweden. [3]
- Gap: Total modules delivered, owners, audited turnover and any named United States project.

## Sources

1. [Company](https://www.harmet.ee/company-2-2/?lang=en) (Harmet)
2. [Production](https://www.harmet.ee/production/?lang=en) (Harmet)
3. [References](https://www.harmet.ee/referenceslist/?lang=en) (Harmet)
4. [Contact](https://www.harmet.ee/contact/?lang=en) (Harmet)
5. [Harmet - wooden element production](https://metsagroup.com/metsawood/news-and-publications/articles/element-manufacturer-harmet) (Metsä Wood)
6. [Nordecon and its subsidiary Nordecon Betoon to build the Estonian largest production hall for modular houses in Harku rural municipality](https://nordecon.com/en/nordecon-and-its-subsidiary-nordecon-betoon-to-build-the-estonian-largest-production-hall-for-modular-houses-in-harku-rural-municipality/) (Nordecon)
7. [Harmet Housing 44 product sheet](https://tradewithestonia.com/wp-content/uploads/2023/05/harmet-housing-44.pdf) (Harmet via Trade with Estonia)