# OFFSITE

Perth maker of timber-framed wall, floor and roof panels for houses and townhouses; in liquidation from late 2026.

- **Operating status:** Restructuring. Administrators were appointed to its operating company in October 2026 after the Welshpool factory shut; they reported about A$40 million owed and liquidators were then appointed. [1][4][5]
- **Momentum:** Contracting
- **Ownership:** Independent
- **Headquarters:** Welshpool, Western Australia, Australia
- **Founded:** 2009
- **Role:** Manufacturer
- **Method:** Panels
- **Material:** Light wood frame
- **Product:** Panels
- **Builds:** Single-family, Multifamily
- **Website:** https://offsite.au/ (no working site of its own when checked)

Checked 2026-11-25. Page: https://nowcitylabs.com/fieldguide/construction/p/offsite-wa/

## Summary by the Lead Analyst

A Perth panel maker that grew from a 2009 concrete formwork business and, under new WA shareholders, moved in April 2025 to an 11,000 sq m Welshpool plant with three framing lines rated for more than 2,500 homes a year. The factory shut in October 2026 with more than 100 jobs lost, about A$40 million owed and orders for hundreds of homes stalled; liquidation followed. No count of homes it supplied was found.

Verify first: Whether a buyer takes the Welshpool framing lines and what happens to the stalled home orders.

## What it is

OFFSITE made timber-framed walls, floors and roofs in its factory and delivered them to sites as framed panels. It offered a library of 15 house, townhouse and medium-density designs engineered for its lines. Its executive chairman said it framed 17 two-story townhouses for one Perth site that were assembled in 45 days. [3]
The business made concrete formwork from 2009. A consortium of Western Australian shareholders led by executive chairman Norm Roberts and chief strategy and operating officer Clarinda Ho bought it, and in April 2025 it moved from Kewdale to an 11,000 sq m Welshpool plant with three HOMAG Weinmann framing lines. [1][3]
The factory shut in October 2026 and more than 100 workers lost their jobs. Administrators from BRI Ferrier WA were appointed to Maneon Pty Ltd, which traded as OFFSITE, on October 21, 2026. They reported about A$40 million owed and recommended liquidation, and the company went into liquidation after no buyer was found among more than a dozen interested parties. [1][2][4][5]

## Key facts

- Founded: 2009, as a concrete formwork maker [3]
- Headquarters: Welshpool, Perth, Western Australia [1]
- Factory: Welshpool, 11,000 sq m, three framing lines [3]
- Employees: More than 100 lost jobs, October 2026 [1]
- Ownership: WA shareholder consortium [1]

## Production and technology

- Production: Large central factory, One Perth plant rated for more than 2,500 homes a year [3]
- Technology: Automated production, Three HOMAG Weinmann framing lines and a Hundegger saw [3]

## Card fields

The same twelve fields every card, table row and comparison shows. A missing value says why: No data, Not published, N/A or Not yet rated.

- Method: Panels
- Materials: Light wood frame
- Products: Panels
- Building markets: Single-family, Multifamily
- Factory: Welshpool, Australia; Kewdale, Australia
- Markets served: Australia
- Demonstrated scale: No data
- Annual capacity: 2,500 homes a year, reported 2026
- Cost: Not published
- Green: Not yet rated
- Value: Not yet rated
- Evidence: Partial · Checked Nov 2026

## Measured

- Capacity per year: 2,500 homes/yr capacity, reported 2026 (company-stated rated capacity, more than 2,500 a year, reported by Wood Central) [3]
- Factory floor area: 118,403 sq ft factory floor area [3]

## Factories

- Welshpool, Western Australia, Australia: 118,403 sq ft, 11,000 sq m; occupied April 2025, shut October 2026 [3]
- Kewdale, Western Australia, Australia: Earlier site, left in April 2025 [3]

## Serves

- Australia (AU) [3]

## Timeline

- 2009 (founded): Began as a concrete formwork business. [3]
- 2025-04 (factory): Moved from Kewdale to an 11,000 sq m Welshpool plant with three HOMAG Weinmann framing lines. [3]
- 2026-10 (layoffs): Shut the Welshpool factory and let go more than 100 workers, stalling orders for hundreds of homes. [2]
- 2026-10-21 (bankruptcy): Administrators from BRI Ferrier WA were appointed to Maneon Pty Ltd, trading as OFFSITE. [4]
- 2026-11 (bankruptcy): Administrators reported about A$40 million owed and recommended liquidation; the company went into liquidation after no buyer was found among more than a dozen interested parties. [1][5]

## Findings by five AI specialists

A level is the strength of the public evidence for one specialist, on a scale of 0 to 4. It is not a grade of the company, and there is no total.

### Materials and Circularity: No public evidence (level 0)

No waste, offcut or material reuse information was found in the sources read.

- Gap: Factory waste figures and timber sourcing.

### Energy and Carbon: No public evidence (level 0)

No energy rating or carbon figure for homes using its panels was found in the sources read.

- Gap: Energy ratings and embodied carbon of its designs.

### Cost and Access: Claims only (level 1)

Its executive chairman cited 17 two-story townhouses framed for one Perth site and assembled in 45 days. Press reported orders for hundreds of homes stalled when the factory shut. No price per home was published.

- Evidence: Wood Central reported the 17-townhouse project in 45 days. [3]
- Evidence: Hard Hat Report reported hundreds of homes on order left in limbo. [2]
- Gap: Prices and how many finished homes used its panels.

### Workforce: Third-party evidence (level 3)

Named press reports more than 100 workers lost their jobs when the factory shut in October 2026. No figures on entitlements paid, training or safety were found.

- Evidence: Wood Central reports more than 100 jobs lost at Welshpool. [1]
- Evidence: Hard Hat Report reports the workforce let go. [2]
- Gap: Whether workers' entitlements were paid in the liquidation.

### Delivery Record: Third-party evidence (level 3)

Press and the administration record confirm the October 2026 shutdown, the October 21 appointment and about A$40 million owed. The plant ran about 18 months at Welshpool. No total of homes supplied is on record.

- Evidence: The appointment of administrators on October 21, 2026 is recorded from the ASIC notice. [4]
- Evidence: Business News reports liquidators appointed. [5]
- Gap: Lifetime output and what the liquidators recover.

## Sources

1. [OFFSITE liquidation vote set for Perth prefab factory](https://woodcentral.com.au/offsite-liquidation-perth-prefab-factory/) (Wood Central)
2. [Perth prefab maker Offsite shuts its factory, stranding orders for hundreds of homes](https://hardhatreport.com/story/offsite-perth-prefab-factory-shut-hundreds-of-homes-stalled/) (Hard Hat Report)
3. [Perth prefab homes factory fits 20 on a block for 16](https://woodcentral.com.au/perth-prefab-homes-site-yield/) (Wood Central)
4. [OFFSITE administration: Maneon Pty Ltd, Welshpool WA](https://www.theopenregister.com/p/deep-dive-2026-10-23-offsite-maneon-administration-advanced-offsite-construction) (The Open Register)
5. [Liquidators appointed to modular builder Offsite](https://www.businessnews.com.au/article/Liquidators-appointed-to-modular-builder-Offsite) (Business News)