Skip to content

Field Guides / Green Infrastructure / North America

BlocPower

Software company and general contractor · Brooklyn, New York, United States · checked November 23, 2026

Leases heat pumps and electrification retrofits to low and moderate income buildings in US cities; based in Brooklyn.

No site of its own when checkedRestructuring

Where it standsLatitude Media reported on August 19, 2026 that BlocPower told investors in a letter it was shutting down and liquidating its assets; no court proceeding or closure date was reported, and its website did not respond on 2026-11-23.[1][4]

Lead Analyst summary

Compiled from the five specialist findings. Read the findings.

BlocPower leases heat pumps and electrification retrofits to low and moderate income buildings and said in 2022 it had electrified over 1,200. City figures cited in named press are smaller than its city plans: 10 buildings in Ithaca against a 6,000-building goal. Latitude Media reported in August 2026 that it told investors it was liquidating, with unsecured creditors not expected to recover. No measured energy or carbon results were found.

Verify first. Owners with a BlocPower equipment lease should confirm who now holds the lease and services the equipment.

What it is

BlocPower was founded in 2014 by Donnel Baird and Keith Kinch to decarbonize homes and buildings in low and moderate income neighborhoods of US cities. Based in Brooklyn, it replaced oil and gas heating with electric air-source heat pumps and other upgrades, usually under a 15-year lease with no down payment, and bid the installation work out to contractors.[1][5]

It raised a $63 million Series A in 2021, $55 million of it debt and $8 million equity, led by American Family Insurance Institute for Corporate and Social Impact, AccelR8 and The Goldman Sachs Urban Investment Group. In 2023 it raised $150 million, including a $130 million debt facility led by Goldman Sachs and a $24 million Series B led by VoLo Earth Ventures, plus nearly $3.6 million from crowdfunding from 2021 to 2025. Menlo Park and Milwaukee never signed contracts and the Ithaca partnership ended; Denver signed a contract for 200 households.[2][6]

Both cofounders resigned in 2024. In July 2026 investors were told it had an offer for part of its software and IP that would not cover its total debt; in August 2026 Latitude Media reported it had told investors it was shutting down and liquidating, with senior creditors Goldman Sachs and VoLo Earth Ventures repaid first and unsecured creditors not expected to recover anything.[1][2]

What public reporting says happened

Causes as a cited source states them.

  • Latitude Media reports that some city contracts stalled after work began, as in Ithaca, or never started, as in Menlo Park and Milwaukee.[1]
  • Latitude Media reports that rising interest rates and electricity prices squeezed its margins.[1]
  • Latitude Media reports that the federal government froze or canceled billions in state home electrification funding in 2025.[1][2]

At a glance

Status
Restructuring
Role
Software company and general contractor
Headquarters
Brooklyn, New York, United States
Serves
NY, CO, CA, GA
Founded
2014
Solution
Heat pumps[5], Building decarbonization[3][5]
Buildings served
1,200 buildings served, 2022[5]

Signature projects

  • Electrify Ithaca, Ithaca, NY. Program manager City plan to electrify about 6,000 buildings; the city's sustainability director said BlocPower ended its work after completing 10 buildings, while the company said it had initiated 14 projects.[2][3]
  • Denver household decarbonization contract, Denver, CO. City contractor Three-year contract signed in 2022 with a goal of decarbonizing 200 households; Latitude Media reports the city paid $826,250 for outreach and heat pumps in one building.[2]
Was this page useful?Send a correction