Makes ReAct, a low-carbon cement made from captured kiln CO2, at a plant beside a California cement works; based in San Jose.

Where it standsRuns a 15,000 ton a year plant in Redding, California, raised an $85 million Series C from venture investors in August 2024, and in October 2026 chose Ste. Genevieve, Missouri, for a 300,000 ton plant with MLC.[3][5]

Lead Analyst summary

Compiled from the five specialist findings. Read the findings.

Fortera, founded in 2019 in San Jose, makes ReAct cement by capturing CO2 from a cement kiln and mineralizing it. Its first plant opened in Redding, California, in April 2024 at 15,000 tons a year, and it lists projects in California and Washington from 2025 and 2026. Its 70 percent emissions cut and project-level figures are company-reported. A 300,000 ton plant with MLC in Missouri is planned, not built.

Verify first. Check supply volume from Redding and the timeline for the Missouri plant before specifying ReAct at scale.

What it is

Fortera was founded in 2019 and is based in San Jose, California. Its ReCarb process attaches to an existing cement plant, captures CO2 from the kiln and mineralizes it into ReAct, a cement that can replace ordinary Portland cement or be blended with it. The company says ReAct emits about 70 percent less CO2 than ordinary cement.[1][3][4]

Its first plant, beside CalPortland's cement works in Redding, California, opened in April 2024 with a design output of 15,000 tons of cement a year and a target of 6,600 tons of CO2 captured a year. The company lists projects using ReAct at UC Berkeley, DPR Construction in Santa Clara, Simpson University in Redding and a Microsoft campus building in Redmond, Washington.[1][2]

It raised an $85 million Series C in August 2024. In October 2026 it and lime producer MLC chose Ste. Genevieve, Missouri, for a planned 300,000 ton a year plant, which Canary Media reports the company aims to open in 2028, and Meta agreed to buy certificates tied to about 200,000 tons of its cement.[3][5][6]

At a glance

Status
Active
Role
Manufacturer and supplier
Headquarters
San Jose, California, United States
Factory
Redding, CA
Serves
CA, WA
Founded
2019
Solution
Low-carbon materials[1][2]

Signature projects

  • ReCarb plant at CalPortland Redding, Redding, CA, 2024. Built and runs the plant A 15,000 ton a year plant beside CalPortland's cement works that takes CO2 from the kiln to make ReAct cement, targeting 6,600 tons of CO2 captured a year.[2][3]
  • Microsoft new campus building, Redmond, WA, 2026. Supplied ReAct Blend cement Concrete with ReAct Blend for a campus building, with Skanska as contractor; the company lists a 37 percent CO2 reduction.[1]
  • UC Berkeley entrance and staircase, Berkeley, CA, 2025. Supplied ReAct Blend cement An entrance, staircase and recycling area poured with Webcor; the company lists a 45 percent CO2 reduction.[1]
  • DPR Construction stairway and ramp, Santa Clara, CA, 2025. Supplied ReAct cement A stairway and ramp at DPR's Santa Clara headquarters; the company says ReAct gave DPR a lower-carbon mix for a high-traffic walkway.[1]
  • Simpson University Darling Center, Redding, CA, 2025. Supplied 15 metric tons of ReAct The Hugh and Hazel Darling Center, built by Gifford Construction, with 590 cubic yards poured.[1]
  • Ste. Genevieve ReAct plant, Ste. Genevieve, MO. Plans the plant with MLC A planned 300,000 ton a year ReAct cement plant at MLC's lime site on the Mississippi River, announced October 2026.[5]