Volumetric manufacturer and developer · Sacramento, California, United States · checked November 19, 2026
Developed steel-framed modular apartments for affordable housing, built in a Vancouver, Washington plant.
No site of its own when checkedUnverified
Where it standsThe website returned a server error (HTTP 526) on November 19, 2026. The latest coverage found is from November 2022, and no source reports a closure, a sale or current activity.[1][4]
Blokable, launched in 2016, developed steel-framed modular apartments for affordable housing, built at a 50,000 square foot plant in Vancouver, Washington. The one delivered project on record is 12 apartments in Auburn, Washington, announced in December 2020 at a stated $125,000 per door. Press reported a $23 million round in 2019 and a move to Sacramento. No coverage after November 2022 was found and its website returns an error, so whether it still operates is unconfirmed.
Verify first. Confirm the company still exists: check the Washington and California business registries before any engagement.
What it is
Blokable designed a steel-structured modular building system and acted as developer and builder of its own projects. A trade profile describes a kit of parts assembled into modules at a warehouse plant in Vancouver, Washington, that could be arranged as anything from single homes to multi-story apartments.[2][5]
Its one completed development in the public record is Blokable at Phoenix Rising, 12 small apartments in Auburn, Washington, announced in December 2020. The company started in Seattle and was described as Sacramento-based by 2022, when it was preparing its system for California codes.[2][4]
Five AI specialists each read the sourced facts on this page for one question. A level measures the public evidence; the company itself is unrated. How the AI Research Team works.
Materials and Circularity
Where do the offcuts go, and can this building be taken apart and used again?
No public evidence
No public evidence on factory waste, reused materials or disassembly of the steel modules was found as of November 2026.
Gap
Waste figures, material sourcing and any plan for disassembly or reuse of modules.
Energy and Carbon
What is the measured energy use or embodied carbon, and who checked it?
Specifics published
The December 2020 Phoenix Rising release lists all-electric systems and energy recovery ventilation and projects 60 percent less heating and cooling energy. A 2022 trade article cites a National Renewable Energy Laboratory report. No metered data from the building was found.
Evidence
The Phoenix Rising announcement lists all-electric systems, an efficient envelope and energy recovery ventilation, and projects 60 percent less heating and cooling energy.[2]
A Modular Building Institute article says a National Renewable Energy Laboratory report on the company pointed toward all-electric, net-zero multifamily housing.[4]
Gap
Metered energy data from Phoenix Rising, the lab report itself, and any embodied carbon figure.
Cost and Access
What does a finished home cost, and who has moved in?
Third-party evidence
One affordable project is documented by the company and a trade body: 12 apartments in Auburn, Washington, announced December 2020, for residents at about 30 percent of area median income, at a stated $125,000 per door. No second delivered project was found.
Evidence
Phoenix Rising has 12 apartments for people earning about 30 percent of area median income; the state paid $125,000 per door and the total cost was $1.5 million.[2]
The Modular Building Institute describes the project as built for Valley Cities, a nonprofit behavioral health provider, with a state capital budget appropriation.[4]
Gap
Any second project, resident outcomes, and costs confirmed by the funder rather than the company.
Workforce
How many people work there, and what happened to them when plans changed?
No public evidence
No public figure exists for the Vancouver, Washington plant workforce or for what happened to it. No layoff notice was found as of November 2026.
Gap
Headcount, wages, training, safety records and any layoff notices.
Delivery Record
How many buildings exist today, and is the company still here?
Third-party evidence
Press and a trade body confirm one 12-unit project (2020) and funding reports of $4.8 million (2017) and $23 million (2019). The website returned an error on November 19, 2026 and no coverage after November 2022 was found, so current status is unconfirmed.
Evidence
Pro Builder reported a $23 million round in December 2019.[3]
The 12-unit Phoenix Rising project is described by both the company and the Modular Building Institute.[2][4]
Gap
Any building delivered in California, any news after 2022, and a filing or notice showing the company is active or dissolved.
Timeline
2016.Founded Launched, according to a December 2020 company statement that dates the start four years earlier.[2]
October 2017.Funding The Columbian reported $4.8 million in investments and a planned ramp-up of the Vancouver, Washington operation.[6]
December 2019.Funding Pro Builder reported a $23 million fundraising round, a new corporate office in Sacramento and plans for a California manufacturing facility.[3]
March 2020.Milestone Supplied a quarantine unit for rapid housing with the Washington State Department of Health during the COVID-19 response.[5]
December 2020.Milestone Announced Blokable at Phoenix Rising: 12 apartments of 280 to 340 square feet in Auburn, Washington, at a stated $125,000 per door.[2]
November 2022.Milestone A Modular Building Institute article described the company as Sacramento-based and working to meet California structural and energy codes.[4]