Panelized manufacturer · Wiri, Auckland, New Zealand · checked November 25, 2026
Fletcher Building's Auckland plant that made wall, floor and roof panels for house cores; closed in 2025.
No site of its own when checkedClosed in 2025
Where it standsFletcher Building said in March 2025 it would close Clever Core by June 30, 2025 because the volumes needed to be viable had not materialized.[3][4]
Fletcher Building's offsite unit opened a NZ$15 million panel plant in Wiri, Auckland in 2019 with a stated capacity of 500 home cores a year and 35 jobs. Fletcher closed it by June 2025, saying volumes never reached viable levels; its housing head cited design lock-in before consent, cyclical demand and stalled Kainga Ora work. No count of homes actually supplied was found.
Verify first. How many home cores the plant actually produced before it closed, which no source read reports.
What it is
Clever Core made the wall, floor and roof panels that form the weathertight core of a house, with insulation, double glazing and allowances for wiring and plumbing fitted in the factory. Trained builders assembled the cores on site. Fletcher said this cut on-site build time by 60 percent and waste by up to 80 percent per home.[1][2]
Fletcher Building opened the Wiri plant in October 2019 with 35 positions and a stated capacity of at least 500 homes a year, first supplying its own developments at Ormiston, Swanson and Beachlands. Press reported the investment as NZ$15 million.[1][2][3]
In March 2025 Fletcher said the plant would close by June 30, 2025 and that a PlaceMakers frame and truss plant would take over the site.[3][4]
What public reporting says happened
Causes as a cited source states them.
Fletcher said the volumes needed to be commercially viable never materialized, citing the market downturn and the industry's reluctance to adopt offsite manufacturing at scale.[3]
Its housing head said offsite designs must be fixed before building and often resource consent, and that consent delays and weather made production hard to plan.[5]
He said internal demand was steady but the business needed government guarantees of demand, and demand dried up when Kainga Ora work stalled.[5]
Five AI specialists each read the sourced facts on this page for one question. A level measures the public evidence; the company itself is unrated. How the AI Research Team works.
Materials and Circularity
Where do the offcuts go, and can this building be taken apart and used again?
Specifics published
Fletcher claimed up to 80 percent less waste per home in 2019; RNZ reported timber offcuts burned as fuel at the Golden Bay Cement plant and insulation offcuts reused. No measured waste figure was published.
Evidence
RNZ reported offcuts used as fuel at Golden Bay Cement and insulation offcuts reused.[2]
Gap
Measured waste per home and any audit of the 80 percent claim.
Energy and Carbon
What is the measured energy use or embodied carbon, and who checked it?
No public evidence
No energy rating or carbon figure for homes built with the panels was found in the sources read.
Gap
Energy performance and embodied carbon of the house cores.
Cost and Access
What does a finished home cost, and who has moved in?
Claims only
The first 100 homes were planned for Fletcher developments at Ormiston, Swanson and Beachlands by the end of 2019. No price, affordable home count or delivered total was found.
Evidence
RNZ reported the first 100 homes were due by the end of 2019 for three Auckland developments.[2]
Gap
How many homes were built and at what price.
Workforce
How many people work there, and what happened to them when plans changed?
Specifics published
The plant opened with 35 positions, some filled through a first-time job seeker program. At closure in 2025 Fletcher said it aimed to redeploy as many staff as possible; how many were redeployed was not reported.
Evidence
Fletcher's 2019 release states 35 positions and the Switch Up recruitment program.[1]
NZ Herald reported the redeployment aim at closure.[3]
Gap
How many workers were redeployed or lost jobs in 2025.
Delivery Record
How many buildings exist today, and is the company still here?
Third-party evidence
Named press confirms the October 2019 opening, the NZ$15 million cost and the March 2025 decision to close by June 30, 2025. No total of homes produced over its life was found.
NZ Herald and BusinessDesk reported the 2025 closure.[3][4]
Gap
Lifetime output of the Wiri plant.
Timeline
August 23, 2017.Milestone Fletcher erected its first house built in a day, a three-bedroom home at Hobsonville.[5]
October 16, 2019.Factory Fletcher Building opened the Clever Core plant in Wiri, Auckland, with capacity for at least 500 homes a year.[1][2]
March 31, 2025.Closure Fletcher announced the plant would close by June 30, 2025, with staff to be redeployed where possible and a PlaceMakers frame and truss plant to use the site.[3][4]