Field Guides / Industrialized Construction / North America

Prescient

Kit and panelized manufacturer and software company · Charlotte, North Carolina, United States · checked November 27, 2026

Designed in its own software and made light-gauge steel structural kits for mid-rise apartments, hotels and dorms.

No site of its own when checkedUnverified

Where it standsIt closed its North Carolina plant in 2022 and filed to close its Arvada, Colorado plant in 2023; no later source says whether the company still trades, and its old web address now points elsewhere.[4][5]

Lead Analyst summary

Compiled from the five specialist findings. Read the findings.

Prescient designed buildings in its own software and made light-gauge steel panels and structural kits for mid-rise apartments, hotels, dorms and senior housing. It reported 57 projects by 2021 and raised 190 million dollars led by JE Dunn and Eldridge that year. It closed its North Carolina plant in 2022 and filed to close its Colorado plant in 2023. No source found says whether the company still operates.

Verify first. Confirm the company still exists and who stands behind warranties on buildings it framed.

What it is

Prescient was founded in Broomfield, Colorado in 2012 and moved its headquarters to North Carolina in 2017, later to Charlotte. It described itself as a software and structural system maker: buildings were designed in its own patented software, and standardized light-gauge steel panels, trusses and columns were shipped as kits for assembly on site.[1][2][4][5][6]

Its first building, the five-story B Street LoHi apartments in Denver, was framed in six weeks in 2013. By May 2021 Construction Dive counted 57 completed projects, including hotels, student and senior housing, barracks and apartments up to 17 stories, such as West Village at UC Davis and Generation Atlanta. In 2020 it held ICC-ES certification for buildings up to 12 stories in seismic zones.[1][2][3]

Eldridge committed 90 million dollars in 2020, and JE Dunn and Eldridge led a 190 million dollar investment and bonding package in 2021 to grow its multifamily work. In 2022 it closed its 135,000 square foot Mebane plant, cutting 83 jobs. In 2023 it laid off 50 people in Arvada and then filed to close that plant, cutting 60 jobs.[2][3][4][5][6]

At a glance

Status
Unverified
Role
Kit and panelized manufacturer and software company
Method
Kit of parts, Panels
Material
Light-gauge steel
Product
Structural kits, Panels
Builds
Multifamily, Hospitality, Student housing, Senior housing
Headquarters
Charlotte, North Carolina, United States
Factory
Mebane, NC +1
Serves
CA, GA, CO, TX
Founded
2012
Units delivered
57 projects delivered, 2021[3]

Production, technology and cost

How the company organizes production, the production technology a source documents, and where a source says it cuts construction cost.

Production

On record
No data

Technology

On record
No data

Cuts cost through

Schedule
Company claimed framing about three times faster than average wood frame[1]
Was this page useful?Send a correction

Prescient

Unverified

No site of its own when checked